John and the gang are pushing hard as completion is scheduled prior to Dec 19th. Ceramic tile re- hallways to start this week-end, lockers on Monday Including CB & TB. Mark ( Lakeside) please connect with John as we only have one week to go / site services /.Looks like indeed our last scheduled site meeting is next Wed. Good Stuff.

Larry

Sent from my iPad