St. Catherine of Alexandria – update

fYI

Sent from my iPad

Advertisements

St Catherine of Alexandria – Critical Path Schedule

I have prepared a critical path schedule for the above project as a means of measure showing progress. The purpose of a critical path schedule is an event cannot start until the previous event is complete. I have allowed an estimated 45 days to completion bring us to Dec 15th. The amount of days include week-ends. Also note site services has been included only if we re- locate catch basin within the construction area. I have identified dates as a milestone allowing us to monitor.

John Poell “May The Force Be With You”

Larry

Sent from my iPad

St. Catherine of Alexandria – update

Steel deck (roof) has been installed. Thought should be given relocating catchbasin allowing us to complete now rather than wait until construction is complete. Windows arriving Monday followed by brick veneer. Parapet Roof to be complete by end of next allowing roofing contractor to start their work. Topping 2nd floor to be applied middle of next week.

Larry

St. Catherine of Alexandria – update

OWSJ have now been installed as we wait for steel deck. We are scheduled to pour topping /2nd floor/ next week.

St. Catherine of Alexandria- update

Steel is now being placed allowing the installation of steel deck. We are scheduled to pour topping 2nd on Friday. We await our windows.

Larry

Sent from my iPad

St. Catherine of Alexandria – we now have SOG

We now have SOG allowing Masonry contractor (JVH)to return and finish interior walls (Main Floor). Roof starts on Tuesday. We are well on way to complete (Dec)

Larry